Metal Roofing and Siding
Installation Guide
Installation details for Delta Rib
, Delta Rib
III,
Nor-Clad
®
, Strata Rib
®
& 2
1
2" Corrugated.
®
Metal Roofing Panels
Installation Guide for Delta Rib
, Delta Rib
III, Nor-Clad
®
, Strata Rib
®
& 2½” Corrugated
March 2024 • ASC Building Products
www.ascbp.com
ASC Building Products
Metal Roofing Installation Guide • March 2024 1
Table of Contents
Section
Introduction..........................................2
Minimum Recommended Tools & Equipment ..........2-3
Delivery, Handling & Storage. . . . . . . . . . . . . . . . . .3
Safety Considerations .................................3
Roof Preparation .....................................4
Map of Typical Roof Conditions.........................5
Trim Locations........................................6
Fastener Placement ...................................6
Fastener Selection ....................................7
Panel Installation .....................................8
Hip/Ridge Flashing....................................9
Universal Ridge Termination ..........................10
Vented Ridge Flashing................................11
Vented Ridge Termination ............................12
Valley Flashing ......................................13
Valley Termination...................................14
Eave................................................15
Eave Flashing Preparation ............................16
Eave with Gutter .....................................17
Gable Flashing.......................................18
Gable/Ridge Transition...............................19
Gable Corner at Eave.................................19
Gable Flashing Preparation ...........................20
Gable Flashing Preparation at Ridge ...................21
Peak Flashing........................................22
Vented Peak Flashing.................................23
Sidewall Flashing ....................................24
Endwall Flashing.....................................25
Vented Endwall Flashing..............................26
Section
Slope Transition - High to Low Slope...................27
Slope Transition - Low to High Slope...................28
Chalet Gable Flashing ................................29
Adjustable Gable Flashing ............................30
Vent Flashing........................................31
Vent/Pipe Flashing Installation Procedure..............32
Skylight Flashing.....................................33
Skylight Flashing (Side)...............................33
Skylight Flashing (Uphill Side).........................34
Skylight Flashing (Downhill Side) ......................35
Procedure for the Installation of
Skylight Flashings ...............................36
Skylight Flashing Preparation ......................36-37
Chimney Flashing ....................................38
Chimney Flashing (Side) ..............................39
Chimney Flashing (Uphill Side) ........................40
Chimney Flashing (Downhill Side)......................41
Valley Top End.......................................42
Valley Dormer .......................................43
Panel End Lap .......................................44
Sealing End Laps & Lapping the Hems..................45
Window/Door Trim Corner Wall Detail..................46
Base Trim, Wall Step, Panel Top Wall Detail.............47
Inside Corner Wall Detail .............................48
Outside Corner Wall Detail............................49
Metal Roofing Installation Guide
Metal Roofing Panels
Installation Guide for Delta Rib
, Delta Rib
III, Nor-Clad
®
, Strata Rib
®
& 2½” Corrugated
®
2 March 2024 • ASC Building Products
www.ascbp.com
In addition to weather tightness, long life, good looks and
economy, ASC Building Product’s Metal Roofing is designed
with ease of installation as a primary consideration. This
guide is intended to help the installer achieve a high level
of quality in the finished product. Please do not hesitate
to contact an ASC Building Products representative for
assistance.
Important Notice
Be sure to read this manual in its entirety before beginning
installation.
This manual is provided to the customers of ASC Building
Products as a guide to assist in the installation of metal roofing.
Use for any other purpose is prohibited. This manual remains the
property of ASC Building Products.
These instructions contain suggested application procedures
only and cannot replace the need for good common sense
and experience. Responsibility for conformance to state and
local building codes, as well as any other ap pli ca ble project
requirements rests with the installer, as does the responsibility
to observe reasonable safety procedures.
ASC Building Products assumes no responsibility for any
problems which might arise as a result of improper installation
or any personal injury or property damage that may occur with
the product’s use.
Introduction
Screw Gun:
Clutch type screw gun with depth locating nose piece allowing
variable torque settings is recommended to insure proper
installation of the screws. The following sockets will be
required:
1
4" and/or
5
16" hex.
Snips:
For miscellaneous panel and lashing cutting requirements.
Three pairs of snips will be required for let edge, right edge,
and centerline cuts.
Electrical Metal Shears:
Used for general metal cutting, such as at the hips and valleys
Chalk Line:
Used to assist in the alignment of panels, lashings, etc
Neoprene Foam Tape:
1
16" x
1
4" roll of tape used for installation of inside and outside
profile closures and panel side laps.
Butyl Mastic Tape:
1
16" x
1
2" roll of tape used for prevention of water infiltration in
lashing to sheet metal applications.
Caulk:
Butyl or urethane sealant used to inhibit water infiltration.
Caulking Gun:
For miscellaneous caulking and sealing to inhibit water
infiltration.
Blind Rivet Hand Tool:
Used for miscellaneous lashing and trim applications.
Marking Tools:
Indelible markers, pencils, or scratching tools.
Minimum Recommended Tools
& Equipment
Note:
It is recommended that metal roofing be applied on roofs with
a minimum slope of 3 inches per foot (3:12).
* The details contained in this guide are shown over a plywood
substrate. Details remain essentially the same for either a solid
substrate (plywood/OSB or steel decking), spaced framing or
intermittent support conditions with only the fastener type
changing. Where spaced framing is used, perimeter supports for
lashings must be considered.
** Each lashing part in this guide has been assigned a part num-
ber. Each part number contains one or two letters followed by
one or two numbers, for example: (EW17). These part numbers
have been provided for you to make ordering these lashing
parts quick and easy.
Note:
Some erectors prefer to use circular power saws with metal
cutting abrasive blades. While the use of power saws may
be faster, there are some disadvantages that must be
considered:
(1) The edges of metal that have been saw cut are
jagged and unsightly, and are more likely to rust than
sheared edges.
(2) Saw cutting will leave small particles of metal on the
panel surface that will rust and damage the panel
finish if not completely removed.
ASC Building Products
Metal Roofing Installation Guide • March 2024 3
Minimum Recommended Tools & Equipment (Con’t)
Scratch Awl:
Used to mark the steel.
Utility Knife:
Used for miscellaneous cutting.
Electric Drill:
Used to drill holes such as those required for rivet installation.
String Line:
Used for general alignment and measuring.
Tape Measure:
25 foot minimum (another 50 t. is handy).
Locking Pliers:
Standard and “Duckbill” style for miscellaneous clamping and
bending of parts.
Delivery, Handling and Storage
Always check the shipment upon delivery. Check for damage
and check material quantities against the shipping list. Note
any damaged material or shortages at the time of delivery.
Handle panel bundles and individual panels with care to avoid
damage. Longer bundles and panels may require two or more
“pick points” properly spaced to avoid damage that can result
from buckling and/or bending of the panels. Request a copy
of the Long Length Handling Instructions and diagrams from
ASC Building Products customer service as required.
Improper storage of product can result in damage to the
finish known as Wet Stack Staining. Store the panels and
other materials in a dry, well ventilated area and away from
traffic. Elevate one end of the bundle to prevent moisture
from settling on the panels. Be sure that air will be able to
circulate freely around the bundles to avoid the build-up
of moisture. Cover the product with a tarp and allow for air
circulation around and under the tarp and bundle of material.
Minimize field storage of material. Contact with wet cement
should be avoided. Damage due to improper storage is not the
responsibility of ASC Building Products.
Painted panels are shipped with a protective plastic sheeting
or a strippable film coating between all panels. Remove any
strippable film coating prior to installation and in any case, do
not allow the strippable film coating to remain on the panels
in extreme heat, cold, or in direct sunlight or other UV source.
Wear clean cotton gloves when handling unpainted
ZINCALUME
®
-coated panels or lashings to avoid discoloration.
Rollforming die marks (which appear black), particularly at
bends, will be visible.
Wear clean, non-marking, sot soled shoes when walking on
the panels to avoid shoe marks or damage to the finish. Do
not step on the panel seams or ribs. Step only in the lat area
of the panel.
Safety Considerations
Never use unsecured or partially installed panels as a
working platform.
Do not walk on panels until they are in place on the roof
and all of the fasteners attaching the panels to the roof
have been installed.
Metal roofing panels are slippery when wet, dusty, frosty
or oily.
Do not walk on a metal roof when any of these conditions
are present. Wearing sot soled shoes will help minimize
slipping and help prevent damage to the painted surfaces.
Do not walk on the panel seams or major ribs.
When walking on the fully installed roof panels, be sure to
step only in the lat areas of the panels.
Always be aware of your position on the roof relative to
your surroundings.
Take note of the locations of roof openings, roof edges,
equipment, co-workers, etc.
Always wear proper clothing and safety attire.
Wear proper clothing when working with sheet metal in
order to minimize the potential for cuts, abrasions, and
other injuries. ASC Building Products recommends safety
glasses and gloves.
Use care when operating electrical and other power
equipment.
Observe all manufacturer’s safety recommendations.
Roof installation on windy or stormy days can be
dangerous.
Avoid working with sheet metal products on windy
or stormy days.
Metal Roofing Panels
Installation Guide for Delta Rib
, Delta Rib
III, Nor-Clad
®
, Strata Rib
®
& 2½” Corrugated
®
4 March 2024 • ASC Building Products
www.ascbp.com
Roof Preparation
ASC Building Products Metal Roofing can be used in both new
construction and retrofit roofing applications. We recommend the
installation of metal roofing over a continuous rigid substrate such
as plywood/OSB, or over spaced supports. Contact ASC Building
Products for additional information.
The following steps need to be taken to prepare the roof for
installation of metal roofing panels:
New Roofs:
1. Make sure there are no nails or other objects protruding from
the substrates that might puncture the underlayment or the roof
panels. Clean all debris from the roof.
2. Check all details for possible roof penetrations which must be
added to the deck prior to roof panel installation.
3. Cover the entire roof deck with a minimum of 30 lb asphalt-
saturated felt paper. Some synthetic underlayments may be used
in place of felt with ASC Building Products’ roofing. Installer must
ensure they meet the minimum standards of 30 lb felt and that
the underlayment manufacturer has approved them for use with
metal roofing. For applications over spaced framing other types
of moisture barriers may be required. For Class A fire resistance,
see notes below. For installation begin at the eave and roll the
underlayment horizontally (parallel to the eave). Allow each con-
sec u tive course to overlap the previous one 3 inches. Overlap the
ends a minimum of 6" (See illustration #1). Areas of underlayment
that have torn should be replaced or repaired prior to installation
of the metal roof.
Illustration No. 1
6" END LAP
3" SIDE LAP
30# FELT PAPER
UNDERLAYMENT
Constructions Requiring
Class ‘A’ Fire Resistance:
Panel: ASC Building Products’ steel roof panels.
Barrier Sheet (one of the following):
GAF VersaShield
®
Underlayment
Firestone GLAD-GARD™ SA-FR
Polyglass Polystick
®
XFR
Georgia-Pacific DensDeck
®
Rooboard
Additional Ply Sheet (optional): Any UL Classified Type G1, G2 or
G3 base/ply sheet, Type 15, 20 or 30 felt or UL Classified Prepared
Roofing Accessory (TGDY) or ASC Building Products’ “AEP Span
Underlayment HT”.
Substrate: 15⁄32” min. plywood or 7/16” min. OSB
Notes:
Obey all local code requirements.
Class A assembly requirements noted above per UL
listing TGFU.R21182. Refer to UL listing for specific
construction limitations.
4. Place an alignment line along the gable end where the first roof
panel will be installed. This line must be parallel to the gable
edge of the roof deck and square with the eave line. Check the
roof for squareness by making a 3' line across the eave. (See
illustration #2).
DIRECTION OF
PANEL APPLICATION
LINE MUST BE
SQARE WITH EAVE
1/4" IN FROM
THE GABLE
ALIGNMENT LINE
Illustration No. 2
Completing the 3' x 4' x 5' triangle should place the 4' edge of
the triangle parallel with the gable. The first roof panel will be
placed parallel with this line. Slight variations or out-of-square
conditions up to 3" can be covered by the gable trims shown on
page 18.
5. It is very important to measure the entire length of the roof from
gable to gable. Correct placement of the panels will allow the
panel’s ribs on each side to be covered by the gable lashing shown
on page 18. This will create a symmetrical appearance on both
gables. Should this be impractical, the adjustable gable detail on
page 30 can be used.
Note:
In areas where snow, ice, and heavy rain conditions exist, a high
temperature cold-applied rubberized underlayment , like AEP
Underlayment HT, should be used in lieu of felt in the valleys. Felt
on the remainder of the roof will lap over the membrane where
the two meet. See Valley page 13.
Existing Roofing:
Some jurisdictions will allow reroofing over existing roofing without
the need for tearoff. Check with your local codes or building
department for your specific requirements.
For best results, Roofing requires a relatively smooth and lat
substrate. Application over rough and/or uneven surfaces is not
recommended, for example, wood shingles. If the roof is to be
stripped down to the existing decking, follow the procedures for
new roofs on page 4. Be sure to check the existing roof and repair
any damaged areas prior to installation of the new roof system.
Note:
Do not apply metal roofing over roofs with structural
damage or trapped moisture.
ASC Building Products
Metal Roofing Installation Guide • March 2024 5
The following steps should be taken when installing ASC Building Products’ Metal Roofing over existing
roofing:
1. Inspect the roof for damage and make the necessary
repairs to achieve a lat plane for the metal roof panels.
Wood shingles should be removed.
2. Secure any warped or loose roofing.
3. Make sure that there are no nails or other objects
protruding from the roof that might puncture the new
underlayment or the new roof panels.
4. Remove all moss and other debris from the roof.
5. Cut off any overhanging roofing lush with the roof deck
and remove all hips, ridge caps, and penetration lashings.
6. Metal debris/shavings should be removed from the roof
progressively and daily to prevent immediate corrosion
and scratching of the top coat.
7. Follow the directions on page 4, #2 through #5 on roof
preparation.
Map of Typical Roof Conditions
For suggestions on how to trim lashings in the different areas, please refer to the following pages:
Flashing Page(s)
Adjustable Gable.................................. 30
Chalet Gable ......................................29
Chimney .......................................38-41
Eave...........................................15-16
Endwall........................................25-26
Gable ...................................10, 12, 18-21
Gutter ............................................17
Flashing Page(s)
Peak .............................................22
Pitch Transition.................................27-28
Ridge ...........................................9, 11
Sidewall Flashing ..................................24
Skylight........................................33-37
Valley....................................13-14, 42-43
Vent...........................................31-32
Metal Roofing Panels
Installation Guide for Delta Rib
, Delta Rib
III, Nor-Clad
®
, Strata Rib
®
& 2½” Corrugated
®
6 March 2024 • ASC Building Products
www.ascbp.com
Prevailing Weather Sheeting Direction
Neoprene or
Butyl Mastic (Typ)
Nor-Clad
®
(36" Coverage)
Strata Rib™ (36" Coverage)
Delta Rib III (36" Coverage)
Delta Rib (24" Coverage)
2-1/2" Corrugated (21-1/3" Coverage) Roof Applications
2-1/2" Corrugated (24" Coverage) Wall Applications
Lap Stitch Screw (Typ)
Woodscrew (Typ
)
or
Fastener Placement
Trim Locations
EAVE FLASHING
BOTTOM
CLOSURE
SINGLE TRACK
COVER
DOUBLE TRACK
COVER
MATCHING
FIBERGLASS
JAMB
TRIM
UNIVERSAL
ENDWALL
GABLE TRIM
UNIVERSAL
RIDGE
UNIVERSAL
SIDEWALL
TOP CLOSURE
PIPE FLASHING
BASE
TRIM
OUTSIDE
CORNER
C-METAL
INSIDE
CORNER
MAXIMUM RECOMMENDED
FASTENER ROW SPACING*
36" (See notes below)
Notes:
Lap panels away from prevailing weather. Use only those accessories specifically designed for use with this product. Use only galvanized or ZINCALUME
®
-
coated fasteners. Isolate roofing and lashings from contact with dissimilar metals. Fastener selection will vary based upon - see chart on following page. The
use of neoprene or butyl mastic tape along the sidelaps, as shown above, is always recommended for roofs. Lap stitch screws should be placed at 16" o.c.
maximum.
*The maximum recommended fastener row spacing is based on 2018 IBC/IRC 115 mph wind speed and an exposure rating of “B” (protected) for typical build-
ings. Refer to IAPMO-UES Building Code Compliance Report #ER-0550 for a more complete list of panel attachments and performance data. More efficient panel
attachment patterns may be available.
ASC Building Products
Metal Roofing Installation Guide • March 2024 7
No. 9 x 1", 1
1
2", 2", 2
1
2", 3" Wood Screw
1
4" Hex
Head
Panel to dimensional lumber
Panel to plywood/OSB minimum
7
16" thick.
Trim and side lap attachments.
Trim and side lap attachments.
Trim-to-trim or
trim-to-panel attachments.
Panel to purlin or deck attachments
No. 14 x 1", 1
1
2" Wood Screw
5
16" Hex Head
No. 12 x
3
4" Stitch Screw
1
4" Hex Head
(compatible with No. 9 Wood Screw)
No. 14 x
7
8" Lap Self Driller
5
16" Hex Head
(compatible with No. 14 Wood Screw)
Stainless Steel Rivet
1
8" x
1
8"
No. 12 x 1", 1
1
2", 2", 2
1
2" Self Driller
5
16" Hex Head
Fastener # Description Use
Fastener Selection
Notes
• The table above shows the metal roofing panel fasteners provided by ASC Building Products.
Refer to the panel installation, lashing details, and fastener placement pages of this manual
for specific fastener usage. See page 6 for fastener spacing.
• Panel attachment screws must be long enough to penetrate through the roof decking at least
3
8", or penetrate into solid lum ber at least one inch.
• All screws must be coated to provide protection against corrosion.
• Exposed fasteners should have sealing washers and be the same color as the parts they
attach.
• Roofing nails will also be required, but are not furnished by ASC Building Products. They are
typically used to temporarily hold a lashing in place that needs to be installed prior to the
panels.
• Screws must be properly driven to ensure proper seal and holding strength. Do not under
drive or overdrive the screws. Recommended drill speed is 2000 rpm. Use of a depth-sensing
nosepiece will aid in properly driving screws.
Proper Installation of
Gasketed Fasteners
Correctly
Driven
Under
Driven
Over
Driven
Metal Roofing Panels
Installation Guide for Delta Rib
, Delta Rib
III, Nor-Clad
®
, Strata Rib
®
& 2½” Corrugated
®
8 March 2024 • ASC Building Products
www.ascbp.com
1"
1"
ASC'S LIGHT
GAUGE ROOFING
Panel Installation
GENERAL
Study the details section of this manual prior to the
installation of the panels. Pay close attention to
the following:
• Flashings that need to be installed prior to the panels
include Valley, Eave, Vented Eave, Adjustable Gable and
Chalet Gable.
• Apply sealant or mastic tape to the pre-installed
lashings as shown in the detail section of this manual.
SEE PAGE 6 & 7 FOR
FASTENER PLACEMEN
AND SELECTION
1" OVERHANG
ILLUSTRATION #3
ILLUSTRATION #4
PROCEDURE
1. Install eave trim, valley trim and inside closure prior to
panel installation.
2. Align the edge of the first panel with the alignment line
constructed along the start gable. (See page 4 item 4
and illustration #3 below). Allow the panel to overhang
the eave 1" minimum.
3. Check the downhill end of the panel. If the panel length
is correct, the panel should overhang 1" past the eave
trim as shown below in illustration #4. Also, the panel
should not extend past the centerline of the ridge. (See
page 9)
4. Ater the first panel is properly aligned, fasten per the
fastener placement and spacing guidelines on page 6.
5. Lay down the second and third panels, checking
alignment, making sure they are square. This will ensure
that a sawtooth effect at the eave and ridge is avoided.
6. Metal debris/shavings should be removed from the roof
progressively and daily to prevent immediate corrosion
and scratching of the top coat.
ASC Building Products
Metal Roofing Installation Guide • March 2024 9
2"
1 7/8"
3/4"
1/2"
1/2"
3/8" HEM
7"
7"
2 1/8"
UNIVERSAL RIDGE (R1)
2. #14 WOOD SCREW
SEE ILLUSTRATION
ON PAGE 7
TOP POLYETHYLENE CLOSURE SET
IN SEALANT ALL AROUND
(SEE PROCEDURES)
ASC'S LIGHT
GAUGE ROOFING
3. #12 x 3/4" STITCH SCREW
OR
4. #14 x 7/8" LAP SELF DRILLER
@ EACH RIB OR 8" O.C.
FOR 2-1/2" CORRUGATED
3-3/4"
3-1/2"
1/2"
135º TYP.
3/8" HEM
2"
1 7/8"
3/4"
1/2"
1/2"
3/8" HEM
7"
7"
2 1/8"
UNIVERSAL RIDGE (R1)
2. #14 WOOD SCREW
SEE ILLUSTRATION
ON PAGE 7
TOP POLYETHYLENE CLOSURE SET
IN SEALANT ALL AROUND
(SEE PROCEDURES)
ASC'S LIGHT
GAUGE ROOFING
3. #12 x 3/4" STITCH SCREW
OR
4. #14 x 7/8" LAP SELF DRILLER
@ EACH RIB OR 8" O.C.
FOR 2-1/2" CORRUGATED
3-3/4"
3-1/2"
1/2"
135º TYP.
3/8" HEM
Hip/Ridge Flashing
Procedures
Caulk the bottom and sides of the polyethylene closure.
Set the closure as shown above and caulk the top. The
closure is optional if the panel is turned up and caulked
at the sides near the rib.
• Fasten the ridge cap using stitch screw at each rib or 8"
o.c. for 2-1/2” Corrugated.
Close the ends of the universal ridge cap by cutting and
folding material at each end. Fasten with rivets. (see
page 10)
• Caulk, lap and rivet sequential ridge lashings.
(see page 45)
R1
R3
R4
Note: “R1” is a universal hip/ridge. A standard hip/ridge, “R3
& R4”, is also available.
Note: The gable lashing must be installed prior to
installation of the ridge (see page 18).
Metal Roofing Panels
Installation Guide for Delta Rib
, Delta Rib
III, Nor-Clad
®
, Strata Rib
®
& 2½” Corrugated
®
10 March 2024 • ASC Building Products
www.ascbp.com
Universal Ridge Termination
UNIVERSAL RIDGE (R1)
BUTYL MASTIC TAPE
OR NEOPRENE CLOSURE
TO CLOSE OFF THE RIDGE
3. STITCH SCREW 1/2"
FROM EDGE OF GABLE
GABLE
CAULK AND RIVET
SEE PAGE 21 FOR
GABLE PREPARATION
OVERHANG UP TO 4"
THEN FIELD TRIM TO 1" OVERHANG
1"
ASC Building Products
Metal Roofing Installation Guide • March 2024 11
1 7/8"
6 3/4" 6 3/4"
3/8" HEM
1 7/8"
1 1/8"
1 1/8"
3/8" HEM
SCREEN BY OTHERS
VENTED RIDGE (R2)
ASC'S LIGHT
GAUGE ROOFING
2"
TOP CLOSURE
C-METAL (C1)
2. #14 WOOD SCREW
SEE ILLUSTRATION
ON PAGE 7
3. #12x3/4" STITCH SCREW
OR
4. #14x7/8" LAP SELF DRILLER
@ EACH RIB OR 8" O.C.
FOR 2-1/2" CORRUGATED
AIR
FLOW
7/8"
2”
1”
3/8" HEM
*
Vented Ridge/Hip Flashing
Procedures
Substrate should be held back 2" from each side of the
ridge.
Attach the screen at each panel rib sandwiching the top
closure in place. Ensure screen is pulled tight to avoid
sagging.
Fasten the vented ridge using stitch screw at each rib or 8"
o.c. for 2-1/2” Corrugated.
Caulk, lap and rivet sequential lashings.
(see page 45).
Close the ends of the ridge cap by cutting and folding
material at each end. Fasten with rivets and caulking
joints. (see page 12).
Slopes greater than 6:12 may require special
ridge dimensions.
For SFS VistaVent
®
or ProfileVent
®
alternate venting, use
lashing detail on page 9 and substitute clusure with vent
material.
R2 C1
Note: The gable lashing must be installed prior to
installation of the ridge (see page 18).
The screening shown creates a barrier for insects and birds
while allowing for ventilation.
For snow and heavy rain environments, please inquire
about other optional Vented Ridge details.
*Consult applicable building codes to ensure ridge vent screening meets minimum material requirements.
Metal Roofing Panels
Installation Guide for Delta Rib
, Delta Rib
III, Nor-Clad
®
, Strata Rib
®
& 2½” Corrugated
®
12 March 2024 • ASC Building Products
www.ascbp.com
Vented Ridge/Hip Termination
CUT AND TRIM SIMILAR
TO GABLE (SEE PAGE 21).
FOLD DOWN OVER END TABS.
CUT AT BENDS 1"
AND FOLD IN 90˚
VENTED RIDGE (R2)
CAULK
CAULK AND RIVET
GABLE
SEE GABLE PREPARATION
@ RIDGE (PAGE 21)
ASC Building Products
Metal Roofing Installation Guide • March 2024 13
Procedures
Place a second layer of 36" roof underlayment in the
valley center line with 18" of roof underlayment on each
side.
Starting at the low end, trim and place the valley lashing
so it overhangs the eaves 1". (see page 14)
Caulk and lap the subsequent valley lashings a
minimum of 8".
Typical polyethylene closures cannot be installed
diagonally across a miter cut panel. At mitre cuts, use
universal Emseal
®
closures parallel to the center of the
valley.
• Field cut the panels holding a minimum of 4" back from
the valley as shown. Larger valleys without the center
“V”, may be required in snow country installations.
Install the panels over the valley lashing using #14
wood screws through the Emseal closure strip.
Space panel fasteners no further apart than as shown
on Page 8.
When valleys are required, install sidelap neoprene or
butyl mastic tape along the sidelap a minimum of 10”
up from the panel edge.
4"
2"
1"
13"
13"
'W' VALLEY (V1)
ASC'S LIGHT
GAUGE ROOFING
2. #14 WOOD SCREW
SEE ILLUSTRATION
ON PAGE 7
INSTALL EMSEAL
®
CLOSURES
DIAGONALLY ACROSS THE BOTTOM
SIDE OF THE PANEL AND
SET IN SEALANT ALL AROUND
SEE NOTE
BELOW
1" TYP
IF PAINTED,
THIS SIDE
19-7/16"19-7/16"
Valley Flashing
V1
V2
Note: Refer to applicable building codes to ensure roof
valley construction meets code requirements. Certain
jurisdictions, like wildfire prone areas, may require
different construction methods or materials.
Note: In areas where snow, ice and heavy rain conditions
exist, panels may need to be held back more than 4" and
the valley lashing overall width must be increased. A high
temperature cold-applied rubberized underlayment should
be used extending at least 3' up from the center of the
valley on each side.
Metal Roofing Panels
Installation Guide for Delta Rib
, Delta Rib
III, Nor-Clad
®
, Strata Rib
®
& 2½” Corrugated
®
14 March 2024 • ASC Building Products
www.ascbp.com
1"
1"
4"
MIN
VALLEY
FOLD TABS DOWN 90˚
REMOVE THIS MATERIAL
SEE VALLEY (PAGE 13) FOR
FASTENING & SEALING REQUIREMENTS
EAVE
EMSEAL
®
CLOSURE
FILL END
WITH SEALANT
Valley Termination
ASC Building Products
Metal Roofing Installation Guide • March 2024 15
ASC'S LIGHT
GAUGE ROOFING
2. #14 WOOD SCREW
SEE ILLUSTRATION
ON PAGE 7
1"
O.H.
EAVE (E1)
BOTTOM POLYETHYLENE
CLOSURE SET IN
SEALANT ALL AROUND
ROOFING NAILS
OR TRIM SCREWS
1/2"
1 3/8"
1 3/8"
2"
1/2"
3/8" HEM
3-3/8"
4-3/8"
3/8" HEM
1/2"
3"
2"
1/2"
3"
1/2"
3"
1/2"
4 3/8"
2"
1 1/2"
1/2"
3"
2"
Procedures
Attach the eave lashing using roofing nails or trim
screws evenly spaced to temporarily secure lashing
prior to installing panels.
Caulk and lap the lashing a minimum of 3".
(see page 45)
Panels should overhang the eave 1" minimum.
Eave and Vented Eave Flashings
This lashing must be installed prior to the panels.
ER1
ER2
E2E1 E4 E5E3
Vented Eave
Metal Roofing Panels
Installation Guide for Delta Rib
, Delta Rib
III, Nor-Clad
®
, Strata Rib
®
& 2½” Corrugated
®
16 March 2024 • ASC Building Products
www.ascbp.com
1"
1"
REMOVE THIS MATERIA
L
EAVE
REMOVE THIS MATERIAL
EAVE
BEND TABS
HERE @ 90˚
Eave Flashing Preparation
Use this lashing where eave meets gable
STEP 1
STEP 2
Note: Length of eave must allow 1" to
extend past gable fascia.
ASC Building Products
Metal Roofing Installation Guide • March 2024 17
Eave With Gutter
Note: This lashing must be installed prior to the panels.
Procedures
Underlayment should be installed over top of eave (E3)
lashing (underlayment not shown).
Temporarily attach eave lashing using roofing nails or trim
screws to secure lashing prior to installing panels.
Caulk and lap the lashing a minimum of 3".
(see page 45)
Panels should overhang the eave a minimum of 1".
ASC Building Products recommends that a licensed gutter
contractor install gutters.
1 3/8"
1 3/8"
1/2"
ROOFING NAILS
OR TRIM SCREWS
2. #14 WOOD SCREW
SEE ILLUSTRATION
ON PAGE 7
1"
O.H.
BOTTOM POLYETHYLENE
CLOSURE SET IN SEALANT ALL AROUND
GUTTER
ATTACH PER
MANUFACTURER'S
RECOMMENDATIONS
EAVE (E3)
E3
Metal Roofing Panels
Installation Guide for Delta Rib
, Delta Rib
III, Nor-Clad
®
, Strata Rib
®
& 2½” Corrugated
®
18 March 2024 • ASC Building Products
www.ascbp.com
5"
5/8"
3/8" HEM
4"
5/8"
3/8" HEM
1 1/8"
1/2"
2 3/4"
4"
1/2"
1 1/4"
BUTYL MASTIC TAPE
2. #14 WOOD SCREW
@ 24" O.C.
ASC'S LIGHT
GAUGE ROOFING
3. #12 x 3/4" STITCH SCREW
OR
4. #14 x 7/8" LAP SELF DRILLER
@ 24" O.C.
GABLE (G2)
2. #14 x 1" METAL WOOD
@ 24" O.C.
2"
1-1/8"
3/8" HEM
5/8"
4"
3/8" HEM
1/2"
Gable Flashing
5"
5/8"
3/8" HEM
4"
5/8"
3/8" HEM
1 1/8"
4"
1/2"
1/2"
2"
3/8"
2 3/4"
4"
1/2"
1 1/4"
BUTYL MASTIC TAPE
2. #14 WOOD SCREW
@ 24" O.C.
ASC'S LIGHT
GAUGE ROOFING
GABLE (G4)
2. #14 WOOD SCREW
@ 24" O.C.
G1
G3
G4
Procedures
Place the first roof panel according to the instructions
on pages 4 and 8.
Place butyl mastic tape along lange of gable trim as
shown.
Install the gable lashing by placing it firmly over the
panel. Use color matched wood screws at 24" o.c. to
attach gable trim to the panel and substrate.
Caulk and lap the lashing a minimum of 3".
(see page 45)
• Mitre cut the lashing at the peak to join each side at the
ridge. (see page 21)
Snip and fold the gable at the eave to close the end.
Use rivets to fasten.
Notes: “G1” is a standard gable. Narrower gables, “G3”
and “G4”, are also available.
ASC Building Products
Metal Roofing Installation Guide • March 2024 19
Gable/Ridge Transition
(similar to Endwall)
ASC'S LIGHT
GAUGE ROOFING
GABLE OR SIDEWALL
BUTYL MASTIC TAPE
WITH FASTENERS
RIDGE OR ENDWALL
GABLE
BEND HERE 90˚
RIVET
INSERT EAVE TAB
BEHIND GABLE
EAVE
ASC'S LIGHT
GAUGE ROOFING
GABLE OR SIDEWALL
BUTYL MASTIC TAPE
WITH FASTENERS
RIDGE OR ENDWALL
GABLE
BEND HERE 90˚
RIVET
INSERT EAVE TAB
BEHIND GABLE
EAVE
Gable Corner at Eave
Metal Roofing Panels
Installation Guide for Delta Rib
, Delta Rib
III, Nor-Clad
®
, Strata Rib
®
& 2½” Corrugated
®
20 March 2024 • ASC Building Products
www.ascbp.com
Gable Flashing Preparation
STEP 1
STEP 2
STEP 3
GABLE
REMOVE THIS MATERIA
L
* SEE TABLE
FOR DIMENSION
GABLE
SNIP HERE
REMOVE THIS MATERIAL
2 1/2"
1 1/2"
1 1/2"
SNIP HERE
1"
1"
GABLE
FOLD 90˚
REMOVE THIS MATERIAL
GABLE
REMOVE THIS MATERIA
L
* SEE TABLE
FOR DIMENSION
GABLE
SNIP HERE
REMOVE THIS MATERIAL
2 1/2"
1 1/2"
1 1/2"
SNIP HERE
1"
1"
GABLE
FOLD 90˚
REMOVE THIS MATERIAL
Roof Pitch Dimension
3:12 2"
4:12 1
7
8"
5:12 1
11
16"
6:12 1
6
16"
12:12
5
8"
Note: Length of uncut
gable must extend 2
1
2"
past eave fascia.
ASC Building Products
Metal Roofing Installation Guide • March 2024 21
EQUAL
EQUAL
VERTICAL CUT
* SEE TABLE
REMOVE THIS
MATERIAL WITH SNIPS
OR POWER SHEARS
REMOVE THIS
MATERIAL WITH SNIPS
OR POWER SHEARS
RIDGE LINE
14" FOR STANDARD RIDGE
17" FOR VENTED RIDGE
RIDGE LINE
GABLE
RIVET
GABLE
REMOVE THIS
MATERIAL WITH SNIPS
OR POWER SHEARS
EQUAL
EQUAL
VERTICAL CUT
* SEE TABLE
REMOVE THIS
MATERIAL WITH SNIPS
OR POWER SHEARS
REMOVE THIS
MATERIAL WITH SNIPS
OR POWER SHEARS
RIDGE LINE
14" FOR STANDARD RIDGE
17" FOR VENTED RIDGE
RIDGE LINE
GABLE
RIVET
GABLE
REMOVE THIS
MATERIAL WITH SNIPS
OR POWER SHEARS
Gable Flashing Preparation at Ridge
STEP 1 STEP 2
STEP 3 STEP 4
Roof Pitch Dimension*
3:12 1
1
16"
3.5:12 1
1
4"
4:12 1
7
16"
5:12 1
3
4"
6:12 2
3
16"
12:12 4
7
16"
* Dimensions only apply to
G4 Gable Flashing
Metal Roofing Panels
Installation Guide for Delta Rib
, Delta Rib
III, Nor-Clad
®
, Strata Rib
®
& 2½” Corrugated
®
22 March 2024 • ASC Building Products
www.ascbp.com


r



Y 
PF2









 













ASC LIGHT GAUGE ROOFING













Peak Flashing
Procedures
Fasten roofing panel to substrate at peak.
Caulk the bottom and sides of top-side closure and place
near peak. Locate closures where they will be hidden
underneath peak lashing.
Apply caulk along top of closure, and fasten peak lashing
using stitch screws at every panel rib location.
Caulk, lap, and rivet sequential lashings (see pg. 45).
Close the ends of the peak at gable ends by slitting and
folding material at each end, caulking joints, and fastening
with rivets.
Notes:
1. Peak lashing dimensions noted on this installation detail
based on nominal 1” thick wall facing. Different wall panel
thicknesses may require some adjustments to peak
lashing dimensions and/or positioning of roof assembly
components.
2. Additional blocking may be required at peak to support
peak lashing.
PF2 Roof Pitch Dimension Dimension
3:12-5:12 5-3/8" 5-1/4"
6:12-8:12 6" 5-3/4"
9:12-10:12 6-1/2" 6-1/4"
11:12-12:12 7-1/8" 6-5/8"
b
a
PF2
a
b
ASC Building Products
Metal Roofing Installation Guide • March 2024 23
r


m
J
l


-1 











Cl



PF3








�
-
-
-
-
-

  


r


m
J
l


-1 











Cl



PF3








�
-
-
-
-
-

  


Vented Peak Flashing
Procedures
Substrate should be held back 2” from the peak.
• Locate the panels at the top end of the substrate. Install
C-metal onto end of panel and fasten panel and C-metal
into place. Check panel positioning at eave before
fastening.
• Insert top-side closure onto panel, at C-metal location.
• Attach the screen at each panel rib, sandwiching the
topside closure in place. Ensure screen is pulled tight to
avoid sagging.
• Fasten the vented peak lashing using stitch screws at
panel rib locations.
• Caulk, lap and rivet sequential lashings (see page 45).
• Close the ends of the peak at gable ends by cutting and
folding material at each end. Fasten with rivets and
caulking joints. (see page 12).
Notes:
1. Peak lashing dimensions noted on this installation detail
are based on nominal 1” thick wall facing. Different wall
panel thicknesses may require some adjustments to peak
lashing dimensions and/or positioning of roof assembly
components.
2. Additional blocking may be required at peak to support
peak lashing.
PF2 Roof Pitch Dimension Dimension
3:12-5:12 6-3/4" 7”
6:12-8:12 7-1/2”" 7-7/8”
9:12-10:12 8-1/4”" 8-5/8"
11:12-12:12 9" 9-1/4"
b
a
PF3
C1
a
b
Metal Roofing Panels
Installation Guide for Delta Rib
, Delta Rib
III, Nor-Clad
®
, Strata Rib
®
& 2½” Corrugated
®
24 March 2024 • ASC Building Products
www.ascbp.com
4"
1 1/8"
2"
1/2"
1/2"
3/4"
ASC'S LIGHT
GAUGE WALL PANEL
ROOFING NAILS
OR TRIM SCREWS*
2. #14 WOOD SCREW
SEE ILLUSTRATION
ON PAGE 7
BOTTOM POLYETHYLENE CLOSURE
SET IN SEALANT ALL AROUND
UNIVERSAL SIDEWALL (SW1)
BUTYL MASTIC TAPE
ASC'S LIGHT
GAUGE ROOFING
2. #14 WOOD SCREW
@ 24" O.C.
1-1/8"
3/8" HEM
5/8"
3"
4"
Sidewall Flashing
This lashing must be installed prior to wall panels.
SW1 SW2
Procedures
• The roof should be installed prior to the siding.
• Place butyl mastic tape along the top of the panel
as shown.
• Install the side wall lashing by placing it firmly on the
roofing panel and fastening with the fastener indicated.
• Caulk and lap the lashing a minimum of 3". (see page
45)
* To temporarily secure lashing prior to installing panels.
ASC Building Products
Metal Roofing Installation Guide • March 2024 25
4"
1/2"
1 1/8"
2"
3/4"
1/2"
ROOFING NAILS
OR TRIM SCREWS
2. #14 WOOD SCREW
SEE ILLUSTRATION
ON PAGE 7
ASC'S LIGHT
GAUGE WALL PANEL
BOTTOM POLYETHYLENE CLOSURE
SET IN SEALANT ALL AROUND
3.
4.
#12 x 3/4" STITCH SCREW
#14 x 7/8" LAP SELF DRILLER
@ EACH RIB OR 8" O.C.
FOR 2-1/2" CORRUGATED
OR
UNIVERSAL ENDWALL (EW1)
ASC'S LIGHT
GAUGE ROOFING
TOP POLYETHYLENE CLOSURE
SET IN SEALANT ALL AROUND
2. #14 WOOD SCREW
SEE ILLUSTRATION
ON PAGE 7
3/8" HEM
5"
4"
EW1
EW2
Procedures
• Install sealant on the bottom and top of the
polyethylene closure. Set the closure as shown above.
• Fasten the end wall lashing to the wall with roofing
nails or trim screws to temporarily secure lashing prior
to installing panels.
• Caulk and lap the lashing a minimum of 3". (see page
45)
Endwall Flashing
This lashing must be installed prior to wall panels.
Metal Roofing Panels
Installation Guide for Delta Rib
, Delta Rib
III, Nor-Clad
®
, Strata Rib
®
& 2½” Corrugated
®
26 March 2024 • ASC Building Products
www.ascbp.com
Vented End Wall Flashing
This lashing must be installed prior to wall panels.
Procedures
Substrate should be held back 2" from the wall.
Install sealant on the bottom and top of the polyethylene
closure. Set the closure as shown above.
Fasten the end wall lashing to the wall with roofing nails
at 24" or trim screws to temporarily secure lashing prior to
installing panels.
Fasten the lashing to each rib with #12 x 34" stitch screws.
Place a short bead of sealant on top of each rib as shown.
(8” spacing for 2-1/2” Corrugated)
Caulk and lap the lashing a minimum of 3". (see page 45)
For SFS VistaVent
®
or ProfileVent
®
alternate venting, use
(EW1) for vented endwall lashing detail.
6 3/4"
1 7/8"
3/8" HEM
1 1/8"
4"
2"
ASC'S LIGHT
GAUGE WALL PANEL
BOTTOM POLYETHYLENE CLOSURE
SET IN SEALANT ALL AROUND
VENTED ENDWALL (EW17)
SEALANT AT FASTENER LOCATIONS
ASC'S LIGHT
GAUGE ROOFING
3. #12 x 3/4" STITCH SCREW
OR
4. #14 x 7/8" LAP SELF DRILLER
@ EACH RIB OR 8" O.C.
FOR 2-1/2" CORRUGATED
AIR FLOW
SCREEN BY OTHERS
TOP POLYETHYLENE CLOSURE
SET IN SEALANT ALL AROUND
ROOFING NAILS
OR TRIM SCREWS
2. #14 WOOD SCREW
SEE ILLUSTRATION
ON PAGE 7
OPTIONAL FIBER FILL
FOR SNOW COUNTRY
2. #14 WOOD SCREW
SEE ILLUSTRATION
ON PAGE 7
EW17
ASC Building Products
Metal Roofing Installation Guide • March 2024 27
ROOFING NAILS
OR TRIM SCREWS
2. #14 WOOD SCREW
SEE ILLUSTRATION
ON PAGE 7
BOTTOM POLYETHYLENE CLOSURE
SET IN SEALANT ALL AROUND
PITCH BREAK (PB3)
3. #12 x 3/4" STITCH SCREW
OR
4. #14 x 7/8" LAP SELF DRILLER
@ EACH RIB OR EVERY THIRD
RIB FOR 2-1/2" CORRUGATED
ASC'S LIGHT
GAUGE ROOFING
TOP POLYETHYLENE CLOSURE
SET IN SEALANT ALL AROUND
2. #14 WOOD SCREW
SEE ILLUSTRATION
ON PAGE 7
WOOD BLOCKING
3/8" HEM
SLOPE (S1)
SLOPE (S2)
6"
5"
SPECIFY
ANGLE
Slope Transition - High Slope to Low Slope
This lashing must be installed prior to uphill panels.
Procedures
Install sealant on the bottom and top of the
polyethylene closure. Set the closure as shown above.
Fasten the transition lashing to the substrate with
roofing nails or trim screws to temporarily secure
lashing prior to installing panels.
Caulk and lap the lashing a minimum of 3".
(see page 45)
Attach the uphill panels as shown.
Install wood blocking as needed for support.
Place a small length of sealant on the top of each rib as
shown.
PB3
Metal Roofing Panels
Installation Guide for Delta Rib
, Delta Rib
III, Nor-Clad
®
, Strata Rib
®
& 2½” Corrugated
®
28 March 2024 • ASC Building Products
www.ascbp.com
1"
ASC'S LIGHT
GAUGE ROOFING
ROOFING NAILS
OR TRIM
SCREWS.
2. #14 WOOD SCREW
SEE ILLUSTRATION
ON PAGE 7
PITCH BREAK (PB4)
BOTTOM POLYETHYLENE CLOSURE
SET IN SEALANT ALL AROUND
TOP POLYETHYLENE CLOSURE
SET IN SEALANT ALL AROUND
WOOD BLOCKING
2. #14 WOOD SCREW
SEE ILLUSTRATION
ON PAGE 7
3. #12 x 3/4" STITCH SCREW
OR
4. #14 x 7/8" LAP SELF DRILLER
@ EACH RIB OR EVERY THIRD
RIB FOR 2-1/2" CORRUGATED
SLOPE (S1)
SLOPE (S2)
5"
6"
3/8" HEM
SPECIFY ANGLE
Slope Transition - Low Slope to High Slope
This lashing must be installed prior to uphill panels.
Procedures
Install sealant on the bottom and top of the polyethylene
closure. Set the closure as shown above.
Fasten the transition lashing to the substrate with roofing
nails or trim screws prior to installing the uphill panels.
Caulk and lap the lashing a minimum of 3".
(see page 45)
Attach the uphill panels with a 1" overhang.
Install wood blocking as needed for support.
Place a small length of sealant on the top of each rib as
shown.
PB4
ASC Building Products
Metal Roofing Installation Guide • March 2024 29
Chalet Gable Flashing
This lashing must be installed prior to panels.
Procedures
Attach the chalet lashing using color matched wood screws
spaced at 24" o.c.
Polyethylene closures cannot be installed diagonally across
angle cut panel ends. Use Emseal® closures parallel to cut
edge to seal voids under panel ends.
Field cut the panels holding 5" back from the face of the
lashing as shown.
Attach the panels to the roof along the bottom edge using
#14 wood screws evenly spaced at 4" o.c. and approximately
2” from panel ends at closure location.
Chalet gable to be used with standard eave “E1”.
(see page 15)
G18
5"
3/8" HEM
3 7/8"
5/8"
3/4"
1 5/8"
6"
2"
EMSEAL
®
CLOSURE
SET IN SEALANT
ALL AROUND
ASC'S LIGHT
GAUGE ROOFING
SLOPE
2. #14 WOOD SCREW
SEE ILLUSTRATION
ON PAGE 7
* THIS DETAIL IS ALSO KNOWN AS
A "PROW" OR "DUTCH" GABLE ROOF.
CHALET GABLE (G18)
2. #14 WOOD SCREW
@ 24" O.C.
End of mitre-cut panel
(See Roof Map page 5)
Metal Roofing Panels
Installation Guide for Delta Rib
, Delta Rib
III, Nor-Clad
®
, Strata Rib
®
& 2½” Corrugated
®
30 March 2024 • ASC Building Products
www.ascbp.com
3/8" HOOK
6"
1/2"
4"
1" HOOK
2 1/2"
ASC'S LIGHT
GAUGE ROOFING
ADJUSTMENT AREA
2. #14 WOOD SCREW
SEE ILLUSTRATION
ON PAGE 7
ROOFING NAILS
@ 12" O.C.
STARTER STRIP (SS1)
CAULK OR BUTYL MASTIC TAPE
CAULK HEM
2. #14 WOOD SCREW
@ 24" O.C.
ADJUSTABLE GABLE (G5)
Adjustable Gable Flashing
G5
SS1
Procedures
In many instances, the roof sheet will have to be field
modified (major rib removed along the gable). See roof map
on page 5 and locate “adjustable gable". If gable trims are
used in this location, and as the roof drains from the ridge,
water will low inside the gable trims shown on page 18. The
adjustable gable trim pieces shown above can assist in a
proper roof in stal la tion.
When a major rib on a metal roofing panel occurs over the
roof area within 3" of the edge of the gable, cut the panel
and remove the major rib from the end of the sheet from
the low eave to allow for the placement of the starter strip.
Install the gable trim, extending the horizontal leg 6" uphill
and underneath the eave on the portion of the roof sheet at
the gable/eave intersection.
Locate the placement of the starter strip to insure that the
cut edge of the roof sheet can be inserted into the 1" leg of
the starter strip.
Field caulk inside the open hem and the under side of the
starter strip per the detail on this page and install parallel
to gable.
Note: Locate starter strip to allow proper installation of
adjustable gable trim as shown.
ASC Building Products
Metal Roofing Installation Guide • March 2024 31
Vent Flashing
Procedures
Trim the opening in the lashing to 20% smaller than
the pipe diameter.
Slide the lashing down over the pipe.
Seal between the vent lashing and the roofing with
gunnable caulk and set the lashing.
Form the lashing to fit the profile of the roof.
Fasten the lashing with fasteners at 1" o.c. Refer to the
fastener selection guide on page 7.
Penetrations occurring over spaced supports may
require additional support framing.
A stainless steel draw band should be installed at the
top of the vent/pipe lashing.
A minimum drainage area of 2" should be maintained
between both sides of the lexible vent/pipe lashing
base and the roof panels’ major ribs.
When a penetration occurs through a panel sidelap,
gunnable caulk needs to be installed in the capillary
groove from the penetration to the ridge. This will
prevent water from running downhill in the capillary
groove and into the roof opening. Refer to illustration
#5, above.
VENT / PIPE FLASHING
FASTEN @ 1" O.C.
ROOF PANEL
GUNNABLE CAULK IN CAPILLARY GROOVE FROM
RIDGE/HIP TO UPHILL SIDE OF PENETRATION
SEE PROCEDURES BELOW
ILLUSTRATION #5
Note: For the best drainage when a square-based pipe
lashing is used, one corner of the lexible pipe lashing
should be oriented to the high-side of the roof.
Metal Roofing Panels
Installation Guide for Delta Rib
, Delta Rib
III, Nor-Clad
®
, Strata Rib
®
& 2½” Corrugated
®
32 March 2024 • ASC Building Products
www.ascbp.com
Vent/Pipe Flashing Installation Procedure
STEP 1: Cut
Cut to pipe diameter marked on
Flashers (this is approximately 20%
smaller than the diameter of the
pipe).
STEP 2: Slide
Slide the Flashers down the
pipe, using water to lubricate if
necessary.
STEP 4: Seal
Seal the Flashers by applying
urethane/silicone sealant between the
Flasher and the roof. Use a large slot
screwdriver to press the base down
tightly.
STEP 5: Fasten
Fasten the Flashers with weather-
resistant fasteners to complete the seal.
STEP 3: Form
Form and bend the aluminum base of
the Flashers to fit the surface of the
roof.
Note: For the best drainage when a square-based pipe
lashing is used, one corner of the lexible pipe lashing
should be oriented to the high-side of the roof.
ASC Building Products
Metal Roofing Installation Guide • March 2024 33
DOWNHILL
SEE PAGE 35
UPHILL
SEE PAGE 34
SIDE
SEE BELOW
1.
2.
3.
SLOPE
LENGTH
WIDTH
3 1/2"
2"
3/8" HEM
3.
DOWNHILL
SEE PAGE 37
WIDTH
LENGTH
SLOPE
1.
SIDE
SEE BELOW
2.
UPHILL
SEE PAGE 36
SIDE SKYLIGHT (SK18)
2. #14 WOOD SCREW
@ 4" O.C.
BUTYL MASTIC TAPE
ASC'S LIGHT
GAUGE ROOFING
Skylight Flashing
Wherever possible, position the skylight curb so the ribs of the
roof panels do not interfere with the lashing.
Cut the metal roof panels as close to the let, right and downhill
sides of the curb as possible. Cut the uphill side 6" up from the
curb as indicated above.
Penetrations occurring over spaced supports require
additional support framing.
SK18
(Side)
1 – Skylight Flashing (Side)
Note: Do not fasten the pan-
els within 24" uphill from the
skylight until the penetration
lashing is installed.
Metal Roofing Panels
Installation Guide for Delta Rib
, Delta Rib
III, Nor-Clad
®
, Strata Rib
®
& 2½” Corrugated
®
34 March 2024 • ASC Building Products
www.ascbp.com
6" MIN
2 1/2"
3 1/2"
12"
BOTTOM POLYETHYLENE CLOSURE
SET IN SEALANT ALL AROUND
ASC'S LIGHT
GAUGE ROOFING
2. #14 WOOD SCREW
@ EACH SIDE OF EACH RIB
OR 8" O.C. FOR 2-1/2" CORRUGATED
UPHILL SKYLIGHT (SK16)
SK16
(Uphill)
2 – Skylight Flashing (Uphill Side)
ASC Building Products
Metal Roofing Installation Guide • March 2024 35
5"
2 1/2"
3/8" HEM
3. #12 x 3/4" STITCH SCREW
@ EACH RIB OR 8" O.C.
FOR 2-1/2" CORRUGATED
TOP POLYETHYLENE CLOSURE
SET IN SEALANT ALL AROUND
DOWNHILL SKYLIGHT (SK17)
ASC'S LIGHT
GAUGE ROOFING
2. #14 WOOD SCREW
SEE ILLUSTRATION
ON PAGE 7
SK17
(Downhill)
3 – Skylight Flashing (Downhill Side)
Metal Roofing Panels
Installation Guide for Delta Rib
, Delta Rib
III, Nor-Clad
®
, Strata Rib
®
& 2½” Corrugated
®
36 March 2024 • ASC Building Products
www.ascbp.com
6"
2 1/16"
2"
5"
2"
2 1/2"
SKYLIGHT
ASC'S LIGHT
GAUGE ROOFING
SLOPE
LENGTH
SLOPE
FOLD HERE 90˚
CUT HERE
CUT HERE
REMOVE THIS MATERIAL
CUT HERE
5"
Procedure for the Installation of Skylight Flashings
DOWNHILL SIDE
ILLUSTRATION #6
Skylight Flashing Preparation
RIGHT SIDE FLASHING SHOWN, LEFT
SIDE SIMILAR (MIRRORED)
UPHILL SIDE
The skylight lashing will be 4" wider than
the width of the curb (2" on each side). Cut a
1
8" slot in the two uphill corners of the metal
roofing panel slightly wider than 2", so the
uphill lashing can slide through the two
slots. (See illustration #6).
Adjustments to the horizontal leg dimension
and length of slit may have to be modified
depending on the location of the panels’
major rib.
REFER TO
INSTALLATION VIDEO
FOR CLARIFICATION
ASC Building Products
Metal Roofing Installation Guide • March 2024 37
2"
1"
1"
FOLD HERE 90˚
CUT HERE
REMOVE THIS MATERIAL
CUT HERE
FOLD HERE 90˚
REMOVE THIS MATERIAL
CUT HERE
REMOVE HEM
TO FOLD LINE
Skylight Flashing Preparation (continued)
Procedures
Trim both ends of the uphill and downhill sides of the
skylight lashing as indicated.
Slide the uphill lashing into the slots of the metal roofing
and apply liberal amount of gunnable caulking.
Assemble the skylight as indicated on pages 34-37.
Trim and assemble chimney lashing similarly.
DOWNHILL FLASHING
UPHILL FLASHING
Metal Roofing Panels
Installation Guide for Delta Rib
, Delta Rib
III, Nor-Clad
®
, Strata Rib
®
& 2½” Corrugated
®
38 March 2024 • ASC Building Products
www.ascbp.com
Chimney Flashing
3.
1.
2.
UPHILL
SEE PAGE 40
DOWNHILL
SEE PAGE 41
SIDE
SEE PAGE 39
1.
2.
3.
LENGTH
WIDTH
SLOPE
Note: Procedures for the installation of chimney lashings
are similar to the skylights. (see pgs. 34-37). The reglet**
shown may be deleted if the chimney is clad with siding.
(Lap the siding over the lashing and caulk). Be sure to
specify the slope and the orientation of the chimney
dimensions when ordering this assembly.
** A reglet is a two-piece lashing found on the side of a
wall, chimney or other similar roof penetration.
(see lashing drawing page 40).
ASC Building Products
Metal Roofing Installation Guide • March 2024 39
3/8" HEM
1/2"
3"
3/8" HEM
3/4"
3/8" HEM
6"
2"
GUNNABLE CAULK
ANCHOR BY OTHERS
REGLET (RG16)
GUNNABLE CAULK
SIDE CHIMNEY (CH18)
BUTYL MASTIC TAPE
ASC'S LIGHT
GAUGE ROOFING
2. #14 WOOD SCREW
@ 4" O.C.
CH18
(Side)
RG16
(Reglet)
1 – Chimney Flashing (Side)
Metal Roofing Panels
Installation Guide for Delta Rib
, Delta Rib
III, Nor-Clad
®
, Strata Rib
®
& 2½” Corrugated
®
40 March 2024 • ASC Building Products
www.ascbp.com
6" MIN
2 1/2"
6"
12"
3/8" HEM
1/2"
3"
3/8" HEM
3/4"
GUNNABLE CAULK
ANCHORS BY OTHERS
REGLET (RG16)
GUNNABLE CAULK
UPHILL
CHIMNEY
(CH16)
BOTTOM POLYETHYLENE CLOSURE
SET IN SEALANT ALL AROUND
ASC'S LIGHT
GAUGE ROOFING
2.
#14 WOOD SCREW
@ EACH SIDE OF EACH RIB
OR EVERY OTHER RIB
FOR 2-1/2" CORRUGATED.
CH16
(Side)
RG16
(Reglet)
2 – Chimney Flashing (Uphill)
ASC Building Products
Metal Roofing Installation Guide • March 2024 41
3/8" HEM
5"
5"
3"
1/2"
3/4"
3/8" HEM
3/8" HEM
GUNNABLE CAULK
ANCHORS BY OTHERS
REGLET (RG16)
GUNNABLE CAULK
TOP POLYETHYLENE CLOSURE
SET IN SEALANT ALL AROUND
DOWNHILL CHIMNEY (CH17)
ASC'S LIGHT
GAUGE ROOFING
3. #12 x 3/4" STITCH SCREW
@ EACH RIB OR 8" O.C.
FOR 2-1/2 CORRUGATED
2. #14 WOOD SCREW
SEE ILLUSTRATION
PAGE 7
CH17
(Downhill)
RG16
(Reglet)
3 – Chimney Flashing (Downhill)
Metal Roofing Panels
Installation Guide for Delta Rib
, Delta Rib
III, Nor-Clad
®
, Strata Rib
®
& 2½” Corrugated
®
42 March 2024 • ASC Building Products
www.ascbp.com
Valley Top End
FIELD MITER AND ASSEMBLE
USE EMSEAL
®
CLOSURE
TO CLOSE OFF VALLEY FLASHING
ASC'S LIGHT
GAUGE ROOFING
ROOFING NAIL
VALLEY (V1)
INSTALL EMSEAL
®
CLOSURES
DIAGONALLY ACROSS THE BOTTOM
SIDE OF THE PANEL AND
SET IN SEALANT ALL AROUND
Note: Refer to Ridge and Valley installation details within
this guide for further clarification on those areas.
ASC Building Products
Metal Roofing Installation Guide • March 2024 43
Valley Dormer
FIELD MITER AND ASSEMBLE
ONTO FLAT STOCK
USE EMSEAL
®
CLOSURE
TO CLOSE OFF
VALLEY FLASHING
ASC'S LIGHT
GAUGE ROOFING
ROOFING NAIL
VALLEY (V1)
INSTALL EMSEAL
®
CLOSURES
DIAGONALLY ACROSS THE BOTTOM
SIDE OF THE PANEL AND
SET IN SEALANT ALL AROUND
Note: Refer to Ridge and Valley installation details within
this guide for further clarification on those areas.
Metal Roofing Panels
Installation Guide for Delta Rib
, Delta Rib
III, Nor-Clad
®
, Strata Rib
®
& 2½” Corrugated
®
44 March 2024 • ASC Building Products
www.ascbp.com
2. #14 WOOD SCREW
SEE ILLUSTRATION
ON PAGE 9
BUTYL MASTIC TAPE OR
GUNNABLE SEALANT
6" MIN
SLOPE
6" MIN
SLOPE
BUTYL MASTIC TAPE OR
GUNNABLE SEALANT BETWEEN PANELS
ASC'S LIGHT
GAUGE ROOFING
2. #14 WOOD SCREW
SEE ILLUSTRATION
ON PAGE 7
Panel End Lap
Long Panel End Lap
For panels 28 t. or longer
6" Min
2"
#10 PANCAKE HEAD
2 ROWS
BUTYL MASTIC TAPE OR
GUNNABLE SEALANT BETWEEN PANELS
ASC'S LIGHT
GAUGE ROOFING
SLOPE
2. #14 WOOD SCREW
SEE ILLUSTRATION
ON PAGE 7
Note: Use this detail so that panels can expand and con-
tract independently.
ASC Building Products
Metal Roofing Installation Guide • March 2024 45
1/8"
3"
3"
SNIP HERE
OPEN THE HEM OF BOTH
FLASHINGS TO BE JOINED
USING A SCREWDRIVER OR
SCRATCH AWL.
REMOVE THIS MATERIAL FROM
THE 'INSIDE' FLASHING ONLY.
RE-CLOSE HEMS WITH
'DUCKBILL' PLIERS
CAULK AND RIVET
AS REQUIRED
Sealing End Laps & Lapping the Hems
Typical Flashing Lap
STEP 1
STEP 2
Note: Flashing expansion joints may be required for long
lashing runs (i.e. 40 t. +).
Metal Roofing Panels
Installation Guide for Delta Rib
, Delta Rib
III, Nor-Clad
®
, Strata Rib
®
& 2½” Corrugated
®
46 March 2024 • ASC Building Products
www.ascbp.com
Procedures
When installing metal roofing panels, “B1”, the Drip
Flashing, is preferred at the head.
A horizontal cut, 1" long, needs to be made in the wall
panel at the intersection of the jamb and head trim.
Extend the head trim into this slot, allowing for proper
drainage to the outside of the building.
Concealed neoprene closures let out for clarity. Place
inside closure behind panel at C-metal (C-1) or base
trim (B1)
C1
B1
Wall Details
Window/Door Trim Corner
3/8" HEM
1"
7/8"
2 1/8"
1"
1/2"
3/8" HEM
2"
ASC'S LIGHT
GAUGE WALL PANEL
BASE TRIM (B1)
C-METAL (C1)
BASE TRIM (B1)
(If required)
C-METAL (C1)
(If required)
3. #12 x 3/4" STITCH SCREW
OR
4. #14 x 7/8" SELF DRILLER
@ EACH RIB OR EVERY 8" O.C.
FOR 2-1/2 CORRUGATED
OR
1. #9 WOOD SCREW
2. #14 WOOD SCREW
@ 24" O.C. MAX
C-METAL (C1) OR
BASE TRIM (B1)
ASC'S LIGHT
GAUGE WALL PANEL
C-METAL (C1)
GLAZING AND WINDOW
FRAME BY OTHERS
1. #9 WOOD SCREW
OR
2. #14 WOOD SCREW
@ 24" O.C. MAX
Note: “C1” is shown at head location. “B1”, Base Trim, can
also be used.
ASC Building Products
Metal Roofing Installation Guide • March 2024 47
Procedures
Open framing shown. If installing over plywood/OSB,
use a #14 wood screw for panel attachment.
Concealed neoprene closures let out for clarity. Place
bottom closure behind panel at base trim and top
closure on top of sheet behind “C1” at panel top, if
required.
Wall Details
Top and Bottom Trim
3/8" HEM
1"
7/8"
2 1/8"
1"
1/2"
3/8" HEM
2"
ASC'S LIGHT
GAUGE WALL PANEL
BASE TRIM (B1)
C-METAL (C1)
BASE TRIM (B1)
(If required)
C-METAL (C1)
(If required)
3. #12 x 3/4" STITCH SCREW
OR
4. #14 x 7/8" SELF DRILLER
@ EACH RIB OR EVERY 8" O.C.
FOR 2-1/2 CORRUGATED
OR
1. #9 WOOD SCREW
2. #14 WOOD SCREW
@ 24" O.C. MAX
TOP OF WALL
C1
B1
Metal Roofing Panels
Installation Guide for Delta Rib
, Delta Rib
III, Nor-Clad
®
, Strata Rib
®
& 2½” Corrugated
®
48 March 2024 • ASC Building Products
www.ascbp.com
3/8" HEM
3/8" HEM
3 1/2"
3 1/2"
4"
5/8"
3/8" HEM
1 1/8"
SYMMETRICAL
BUTYL MASTIC TAPE
ASC'S LIGHT
GAUGE WALL PANEL
3. #12 x 3/4" STITCH SCREW
OR
4. #14 x 7/8" LAP SELF DRILLER
@ 24" O.C. MAX
INSIDE CORNER (IC1)
1. #9 WOOD SCREW
OR
2. #14 WOOD SCREW
SEE ILLUSTRATION
ON PAGE 7
IC1
Procedures
Open framing shown. If installing over plywood/OSB,
use a #14 wood screw for panel attachment.
• Nor-Clad
®
panel shown. When installing other metal
roofing panels, use the Universal Inside Corner “IC2”.
In many situations, the last panel installed at the corner
will require that the panel be cut in width. Allow the cut
edge to be covered by the inside corner trim.
Wall Details
Inside Corner
IC2
ASC Building Products
Metal Roofing Installation Guide • March 2024 49
1 1/8"
3/8" HEM
5/8"
4"
3/8" HEM
3/8" HEM
3 1/2"
3 1/2"
SYMMETRICAL
BUTYL MASTIC TAPE
OUTSIDE CORNER (OC1)
ASC'S LIGHT
GAUGE WALL PANEL
1. #9 WOOD SCREW
OR
2. #14 WOOD SCREW
SEE ILLUSTRATION
ON PAGE 7
3. #12 x 3/4" STITCH SCREW
OR
4. #14 x 7/8" LAP SELF DRILLER
@ 24" O.C. MAX
Wall Details
Outside Corner
OC1
OC2
Procedures
Open framing shown. If installing over plywood/OSB,
use a #14 wood screw for panel attachment.
• Nor-Clad
®
panel shown. When installing other metal
roofing panels,use the Universal Outside Corner “OC2”.
In many situations, the last panel on each side will
project beyond the building corner, requiring the
panel to be cut in width. Allow the cut edge to be
covered by the outside corner trim.
All information stated in the catalog is correct at time of printing and subject to change without notice, check our website for the latest version.
© 2008-2024 ASCProfiles LLC. All rights reserved. ZINCALUME
®
is a registered trademark of BlueScope Steel Ltd.
Printed in the USA. 0524 web BR128
Manufacturing Facilities:
Anchorage, Alaska
2441 Cinnabar Loop
Anchorage, AK 99507
West Sacramento, California
2110 Enterprise Boulevard
West Sacramento, CA 95691
Salem, Oregon
4063 Salem Industrial Drive NE
Salem, OR 97303
Customer Service Center
800-272-7023 • 503-390-7174
Spokane, Washington
4111 East Ferry Avenue
Spokane, WA 99202
Customer Service Center
800-776-8771 • 509-536-4097
Corporate Headquarters:
ASC Profiles
2110 Enterprise Boulevard
West Sacramento, CA 95691
Visit us at our website:
www.ascbp.com
®